We have officially started recruiting for our 2011 summer staff. I am confident that it will be an exciting summer. Regardless if the staff is sleeping in cozy cabin or…

0 Comments

Theme & Dates for Summer Camp

Although as of today we do not have one building completed on the new property, we are planning to have camp there next summer. The theme is - Under Construction.…

0 Comments

Shed

On Saturday evening, the trusses were set, the attic floor was installed, and the bracing was finished. We are very thankful for everyone that came and helped work.  Click here for a…

0 Comments

Praise God

Wednesday morning was a very busy morning. We were checking our holes and making them as dry as possible. The building inspector arrived at about 9:00 and approved our holes.…

0 Comments

Mud

Because a crew from APM was scheduled to arrive Thursday morning, we were desperately trying to get the mud out of our foundation holes. We were praying specifically that the…

0 Comments

Winterized Kitchen

Several of you were concerned about Mrs. Fry's kitchen. Well, it is now winterized. Ok, it is not exactly winterized, but we were very thankful for the small tent. The…

0 Comments

Thank You Chad & APM

Several weeks ago we ordered a 30 X 40 pole shed with attic trusses from Chad Fouchie at APM Building Products in Arendtsville, PA. We were debating if we were…

0 Comments

Work Days

We have scheduled three work days at the new property - October 7, 8, & 9. We would love to have you join us for 1, 2, or 3 days.…

0 Comments

Mrs. Fry’s New Kitchen

On Sunday, Ken Estep asked if we could use a triple sink and a SS serving table. We picked up the equipment at 7:00 Monday morning and took it along…

0 Comments