Because of rain the excavators barely worked after Monday of last week. But they are working this week! This is what the lodge site looks like at 10:30 this Tuesday…
Because of rain the excavators barely worked after Monday of last week. But they are working this week! This is what the lodge site looks like at 10:30 this Tuesday…
We started! We started!! Today the excavators started to remove the big hill in preparation for the lodge. Sometimes, we thought this day would never come. To God be the…
Today was a significant day!! We signed our first contract for building the lodge. For $170,300.00 we will get 64,140 lb. of structural steel installed. We will need more steel…
I love it when I can watch the odometer on our car roll over the big round numbers. We have just a little over 1,000 miles until we can celebrate…
At 10:00 on Monday, September 18 we had a hearing with the Moshannon Valley Council of Governments to request a variance for the commercial fire suppression system in the new…
Before summer camp began, we were giving regular updates on the lodge. Recently, however, we have been a bit negligent in keeping you posted. Here are a few updates. As…
Our donor friend told me to go ahead and promote another $25,000 matching gift. He was much slower with the response, so maybe this is the last one. If you…
Today we received a significant check from MORGAN STANLEY for the lodge fund, but there was no indication as to who donated the money. I called three different numbers at…
Typically, on the first of each month we update the lodge page of our website with the amount that God has provided for the lodge. Since the last update on…