Ready for Concrete
Tomorrow, the concrete boom pumper truck should arrive to start pouring the footers.
Tomorrow, the concrete boom pumper truck should arrive to start pouring the footers.
Do you ever wonder what is happening to the lodge at Servant’s Heart Camp. We now have a Live-stream that you can check anytime. Just go to our website and…
We started digging footers today. It is a unique combination of wide footers, narrow footers, deep footers and shallow footers.
Even some people very familiar with the property could not quite picture in their mind where we were putting the lodge. Hopefully, this picture will help.
Because of rain the excavators barely worked after Monday of last week. But they are working this week! This is what the lodge site looks like at 10:30 this Tuesday…
We started! We started!! Today the excavators started to remove the big hill in preparation for the lodge. Sometimes, we thought this day would never come. To God be the…
Today was a significant day!! We signed our first contract for building the lodge. For $170,300.00 we will get 64,140 lb. of structural steel installed. We will need more steel…
I love it when I can watch the odometer on our car roll over the big round numbers. We have just a little over 1,000 miles until we can celebrate…
At 10:00 on Monday, September 18 we had a hearing with the Moshannon Valley Council of Governments to request a variance for the commercial fire suppression system in the new…